On the RoadSunday, November 8
I-195 in East Providence is open again after crews took down the Potter Street Bridge
The 5AM North Providence team
If you drive I-195 through East Providence, all lanes are open again. Crews brought the bridge deck down shortly after 2 a.m. Saturday, working through intense rain. The demolition is part of the Washington Bridge rebuild.
The Potter Street Bridge came down overnight and I-195 reopened
- Nov. 6I-195 closed in both directions late Friday for the demolition.
- Nov. 7The Potter Street Bridge deck came down shortly after 2 a.m.
- Nov. 7The planned 10 a.m. partial reopening was adjusted so all lanes could reopen together.
- Nov. 7All lanes of I-195 in East Providence reopened.
Cleanup delayed the planned 10 a.m. partial reopening, and RIDOT said work was trending ahead of its noon target. Before the closure, interim RIDOT Director Robert Rocchio said the agency was counting on traffic to divert, and RIDOT planned detours onto local streets.
- East detour: Exit 1D, Warren Avenue
- West detour: Exit 2, Broadway, then Warren Avenue
- New Potter Street Bridge: 12 to 18 months of rebuilding planned
The closure by the numbers
- 30%
- of usual I-195 traffic RIDOT was counting on to divert
- 12 hours
- planned length of the full closure
- 30
- extra police and traffic control personnel on Warren Avenue
- Nov. 2028
- expected finish for the Washington Bridge rebuild